Period: March 11, 2026 – June 9, 2026
During this period, the Los Angeles Department of Building and Safety processed 147,761 inspections across 159 inspection types. The overall pass rate was 44%, with a 42% fail rate.
Note: This pilot brief demonstrates the system's capability to generate executive intelligence from LADBS data. Results are categorized using actual LADBS terminology.
| Inspection Type | Total | Pass Rate | Fail Rate |
|---|---|---|---|
| Final | 37,359 | 48% | 38% |
| Rough | 10,542 | 20% | 67% |
| Service/Power Release | 5,859 | 49% | 34% |
| Smoke Detectors | 5,349 | 65% | 21% |
| Inspection | 4,536 | 99% | 0% |
(Minimum 100 inspections)
| Inspection Type | Fail Rate | Volume | Pass Rate |
|---|---|---|---|
| Deputy Wood Construction | 88% | 641 | 12% |
| Deputy Shotcrete | 87% | 439 | 12% |
| Stormwater Drainage | 82% | 149 | 1% |
| Fire Damper Framing | 82% | 123 | 8% |
| Deputy Reinf. Concrete | 77% | 1,559 | 23% |