Period: April 25, 2026 – July 24, 2026
During this period, the Los Angeles Department of Building and Safety processed 198,555 inspections across 161 inspection types. The overall pass rate was 43%, with a 42% fail rate.
Note: This pilot brief demonstrates the system's capability to generate executive intelligence from LADBS data. Results are categorized using actual LADBS terminology.
| Inspection Type | Total | Pass Rate | Fail Rate |
|---|---|---|---|
| Final | 48,666 | 48% | 38% |
| Rough | 15,091 | 19% | 68% |
| Service/Power Release | 7,520 | 50% | 34% |
| Smoke Detectors | 7,040 | 64% | 21% |
| Floor/Roof Diaphrgm/Shear Wall | 5,824 | 37% | 51% |
(Minimum 100 inspections)
| Inspection Type | Fail Rate | Volume | Pass Rate |
|---|---|---|---|
| Deputy Wood Construction | 89% | 861 | 10% |
| Deputy Shotcrete | 84% | 488 | 15% |
| Stormwater Drainage | 82% | 147 | 3% |
| Fire Damper Framing | 81% | 176 | 4% |
| Water Piping or Service | 77% | 563 | 6% |